Skip to content
Home » The Estimating Problem

The Estimating Problem

1

 

The Estimating Problem

 

Kristie Lin

 

Colorado State University Global

 

PJM 500 Module 4 Critical Thinking

 

Dr. Melinda Hollingshed

 

3/7/21

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

2

 

The Estimating Problem

 

Having an accurate estimation of the project timeline is crucial for all stakeholders.

 

Investors want to know when they can start to see a return on their investment, and the project

 

management team needs to deliver the product on time to please their client or investors. If the

 

project timeline comes up short, there could be a high chance that the project would be

 

completed late. Additionally, if there are too many resources allocated for a section of the

 

project, those resources could be wasted. In contrast, if too few resources are allocated, burnout

 

of employees and a prolonged timeline could occur. All of these scenarios are not ideal and can

 

increase project costs or delay the project, which is why choosing the correct method of

 

estimating is pivotal to the success of a project.

 

Case Study Synopsis

 

Barbara’s company had just won a bid for a new project. The estimating team had already

 

submitted their estimates in their proposal, however, Barbara wanted to review the estimates.

 

One issue with the estimates that Barbara had identified was a critical work package that the

 

estimating team predicted would take twelve weeks to complete. With Barbara’s experience, she

 

believed that the estimating team was completely off with their three-point estimate.

 

Throughout the case study, there were multiple methods of estimating mentioned,

 

including triangular distribution, analogy estimating, and expert judgement. Triangular

 

distribution would have estimated the critical work package would be completed in thirteen

 

weeks. According to Peter, who is a grade 9 employee, and considered to be an expert on this

 

work package, the more realistic timeline would be closer to 16-17 weeks. Peter also suggested

 

that to account for the complexity of the project, analogy estimating would have been the better

 

method to predict the estimate.

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

3

 

Even if the estimating team considered adding more man power to the critical work

 

package, Peter believed that additional people would not shorten the schedule, and instead make

 

it worse. The estimating team had also allocated a grade 7 employee full time to the critical work

 

package and predicted that with the grade 7 employee, the work package would be completed in

 

12 weeks. According to Peter’s experience and knowledge, a grade 7 employee would probably

 

take approximately 20 weeks, not 12.

 

Critical Path

 

The critical path of a project is basically the minimum amount of tasks or activities that

 

are required in order for the project to be completed (Project Manager, n.d.). Any alteration or

 

delay with any of these tasks or activities can cause a setback and potentially postpone the

 

delivery date. In the case study, part of the critical path is the critical work package that is under

 

review. The critical path determined by the estimating team was allocated 12 weeks to complete

 

the critical work package. Judging by the opinions of Barbara and Peter, the likelihood of the

 

critical path being extended is very high.

 

Three-Point Estimating

 

As pointed out in the case study, using the three-point estimating process does not

 

account for any complexity factors and it is best utilized for smaller projects that are not as

 

complex as the current project that Barbara is working on (Kerzner, 2017). If the estimating team

 

had followed Peter’s advice and used a combination of analogy estimating as well as expert

 

judgement, the team would have gotten a more accurate estimate. Being realistic about

 

deliverables and timelines will only help the company when it can complete the project on time

 

and not be penalized for a late delivery. It is never a good thing when a company over-promises

 

and under-delivers and in this case, Barbara’s company is at risk of doing so. The three-point

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

4

 

estimate would be over-promising the client considering all the other estimating methods

 

predicted the project would take longer. If the project were delayed, Barbara’s company would

 

have under-delivered.

 

With the three-point estimating method, there can be some advantages to utilizing this

 

process. There is also a point and time of when the three-point estimation would be the best

 

method to employ. Three-point estimating allows organizations to quantify risks and have it built

 

into the project budget (Roseke, 2018). The issue with three-point estimating, on top of not

 

accounting for complexity factors, is that this type of estimating method requires a lot of detailed

 

information that sometimes is not available at the start of a project (Roseke, 2018). It is also very

 

complex to execute. Thus the three-point estimating method was not the right method to use for

 

this project.

 

Estimating Process

 

Before the estimating team submitted their estimates in the proposal, the team should

 

have gathered more information and consulted other experts. They should have collected

 

information on recent experiences with similar projects or work, professional and reference

 

material, market and industry surveys, knowledge of operations and processes, interviews with

 

subject matter experts, and utilize estimating software and databases (Kerzner, 2017). All of this

 

information is critical for the estimating team to have in order to make a good estimate (Kerzner,

 

2017). The project manager should have been consulted as well on the estimates, seeing as how

 

she is responsible for planning, organizing, and directing the project to its completion.

 

Recommendation

 

As far as recommendations go, the company should not just rely on one method to

 

estimate the project schedule, necessary resources, and costs. Because of the complexity of the

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

5

 

project, a combination of analogous estimating as well as parametric estimating might give the

 

company the most accurate estimate of how long the project will really take (Goodrich, 2015).

 

Being able to take into consideration the timeline of similar projects that have occurred in the

 

past should provide the company a good layout of what the current project’s schedule will look

 

like. Parametric estimating is actually said to be more accurate however, taking into

 

consideration of Peter’s expertise, adding an analogous estimation would provide a more realistic

 

estimate (Goodrich, 2015).

 

Conclusion

 

When it comes down to estimating and planning the project schedule, it is wise to consult

 

those with previous experience in the specified area. Referring to similar projects that were

 

completed in the past can also provide a good estimate of how long the project will take. Bottom

 

line is with the complexity of the project, a three-point estimation is not the best method to

 

utilize. Instead, a combination of parametric and analogous estimating would be more accurate

 

and provide a more realistic project schedule.

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

6

 

References

 

Goodrich, B. (2015). Analogous estimating vs parametric estimating. PM Learning Solutions.

 

https://www.pmlearningsolutions.com/blog/analogous-estimating-vs-parametric-estimatin

 

g-pmp-concept-4

 

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and

 

controlling (12th ed.). Hoboken, NJ: John Wiley & Sons.

 

Project Manager. (n.d.). What is the critical path?.

 

https://www.projectmanager.com/critical-path-method

 

Roseke, B. (2018). Three point estimating for the PMP exam. Project Engineer.

 

https://www.projectengineer.net/three-point-estimating-for-the-pmp-exam/#:~:text=Three

 

%20point%20estimating%20is%20a,in%20to%20the%20project%20budget.

 

This study source was downloaded by 100000856080857 from CourseHero.com on 03-07-2024 04:23:02 GMT -06:00

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/ Powered by TCPDF (www.tcpdf.org)

 

https://www.coursehero.com/file/90322509/PJM-500-Module-4-Critical-Thinking-Option-1pdf/

http://www.tcpdf.org

Interested in getting help with this assignment?

Get a professional writing team to work on your assignment!

Order Now
Recent posts
For this final assignment, you will prepare a brief paper detailing the steps undertaken to complete a presentation that disseminates information you assemble
Please choose to answer only one of the 2 following questions. Option 1: In your opinion and based on scientific, peer-reviewed published evidence, does child
At the beginning of the previous academic year, the institution announced it would drop football at the conclusion of the season. The announcement created pub
you will review current research in Personality and provide a critical evaluation of that personality research through an annotated bibliography. An annotated
In Module 5, we considered the third in our three-part series on research design. Specifically, the focus was on the longitudinal studies, in which the resear

Need help with a similar or different Task?

We have the best writers to help you. Hire Writer Now

ORDER NOW